New build programme
Eskom is embarking on a very large infrastructure expansion
programme which has a board-approved budget of
R343 billion up to 2013 and is expected to grow to more
than a trillion rand by 2026. Additional power stations and
major power lines are being constructed in line with our plan
to deliver an additional 16 304MW in generation capacity
by 2017. Ultimately, Eskom will double its capacity to about
80 000MW by 2026.
This massive build programme has been designed such that it
adequately responds to the challenge of electricity availability
and reliability. It has also been aligned with government’s target
of 6% GDP growth between 2010 and 2014.
I am pleased to report that the Eskom build programme is
on track to deliver the additional infrastructure as planned.
We have made excellent progress during the past financial year, and have indeed achieved what we set out to do in
this regard. Ankerlig and Gourikwa power stations – the two
new open-cycle gas turbine stations located in the Western
Cape – were officially opened. The National Energy Regulator
of South Africa (Nersa) granted Eskom the licence to build
the first new coal-fired power station in more than 20 years.
Hitachi Power Africa was awarded a R20 billion contract for
boilers, and Alstom S&E was awarded a R13 billion contract for
turbines for Medupi power station. We also awarded contracts
worth some R31,5 billion for the “Bravo Project”, a coal-fired
power station to be built by 2017 – R18,5 billion to Hitachi Power
Africa for boilers and R13 billion to Alstom S&E for turbines.
Work is well underway on the return to service of the three
previously mothballed power stations – Camden, Komati, and
Grootvlei. The construction of Ingula pumped storage scheme
is also progressing well. We are also on track with several of our
transmission projects.
For the reporting year, capital expenditure of R24,7 billion was
incurred. This was R218 million above the target for the year –
a confirmation that the accelerated programme is on track.
I must pay special tribute to the Eskom team for ensuring that
this all important programme of building new capacity remains
on track notwithstanding all the adversities brought about by an
inadequate reserve margin.
Financial sustainability
Eskom’s massive capacity expansion programme will take the
organisation into a new and exciting, but also very challenging,
phase in its history. Funding the programme is one such challenge
which will test the organisation’s financial sustainability. The
financial health of the organisation has come under pressure
given the increase in primary energy costs and the need to
reduce consumption through demand-side management and
power-conservation projects.
The profit for the year for the Eskom group was R974 million
(2007: R6 476 million) after taking into account the fair value loss
on embedded derivatives of R143 million (2007: fair value gain
of
R4 305 million).
The profit for the year for the company was R1 333 million
(2007: R6 030 million) after taking into account the fair value loss
on embedded derivatives of R149 million (2007: fair value gain
of
R4 131 million).
Primary energy costs (mainly coal and diesel) increased from
R13 040 million in 2007 to R18 314 million in 2008, while
the growth in sales only amounted to 2,9%. This was mainly due
to an increase in coal price and the extended use of the opencycle
gas turbines due to the reduced reserve margin in October
2007 and the early months of 2008.
The higher primary energy cost that Eskom incurred in 2006/7
and 2007/8, together with projections for the 2008/9 financial
year prompted the organisation to approach Nersa with the
view to re-open tariff discussions. It was clear that Eskom,
in the absence of any decisive action, was on a financially
unsustainable path. During the financial year, Standard and
Poor’s (credit rating agency) placed Eskom on “credit watch”
with negative implications, reinforcing the need to secure our
financial health.
Going forward, Eskom will require significant contributions from
all sources of capital namely price increases, funding support
from government, and borrowings from both the local and
international market.
On 18 June 2008, Nersa announced a decision to increase
the average price by 27,5% in 2008/9, including the previous
decision of 14,2% in December 2007, ie an additional increase
of 13,3%. It is notable from the decision that the regulator indicated that a mechanism would be developed to
take into account unforeseen changes in primary
energy costs and other costs. Furthermore, the
regulator gave a projection of the price path of
between 20% and 25% per annum for the next multiyear
price determination assuming that the current
economic climate continues to prevail and Eskom’s
capital expenditure remains as currently stated.
This decision by Nersa is of deep significance for it
constitutes a paradigm shift and signals a completely new,
improved tariff path into the future. The power industry
is now on a path to financial sustainability.
The South African government, which is the sole
shareholder of Eskom, has announced its intention to
support Eskom initially with a R60 billion subordinated
loan to be drawn down in tranches in the next five years.
Pressure in the global credit markets is an additional
challenge for Eskom’s funding opportunities. Alternative
funding sources are continually being pursued in order to
maximise funding options.
Internal efficiencies
As part of ensuring the long-term financial sustainability
of the organisation, we have put in place a programme to
maximise internal efficiencies. Two years ago, we commenced
the procurement and supply chain strategic sourcing initiative
with the aim of securing the supply of goods and services for
the organisation in the most optimal manner. I am pleased
to report a R3,1 billion savings achieved this year against a
target of R1,5 billion. This brings the total inception-to-date
savings to R3,9 billion against the overall savings target of
R7,8 billion over the five years to 2011. We are confident that
such a target will be achieved. |