| Key performance area |
Key performance indicator |
Unit of
measure |
Target
2008 |
Actual
2008 |
Actual
2007 |
Exceeded /
not
achieved |
Capital and
financial
efficiency |
Return on average capital employed (ROACE) |
Budget (%) |
≥ 6,1 |
5,4 |
9,7 |
not achieved |
| Earnings before interest and tax margin (EBIT) |
Budget (%) |
≥ 11,5 |
9,2 |
16,9 |
not achieved |
Capital
expansion (infrastructure
and capital expenditure) |
Generation capital expenditure |
Budget (Rm) |
≥ 9 940 |
11 004 |
7 056 |
exceeded |
| Transmission capital expenditure |
Budget (Rm) |
≥ 2 171 |
2 394 |
1 170 |
exceeded |
| Generation technical plan expenditure
(investment in existing infrastructure) |
Budget (Rm) |
≥ 3 703 |
3 461 |
2 942 |
not achieved |
| Distribution capital expenditure |
Budget (Rm) |
≥ 3 476 |
3 886 |
3 430 |
exceeded |
| Generation capacity installed and commissioned |
Plan (MW) |
≥ 1 041 |
1 061 |
1 360 |
exceeded |
| Transmission lines installed |
Plan (km) |
≥ 270 |
246 |
430 |
not achieved |
| Transmission MVA installed |
Plan (MVA) |
≥ 295 |
1 295 |
1 000 |
exceeded |
Operating
efficiency and effectiveness |
Major incidents (transmission system minutes lost) |
Plan |
≤ 1 |
6 |
2 |
not achieved |
- severity degree one ( ≥ 1, but less than 10 minutes)
|
|
≤ 1 |
5 |
1 |
|
- severity degree two ( ≥ 10, but less than 100 minutes)
|
|
0 |
0 |
1 |
|
- severity degree three ( ≥ 100 minutes)
|
|
0 |
1 |
0 |
|
| Transmission system minutes lost (<1) |
Plan (SML) |
≤ 3,9 |
3,56 |
3,67 |
exceeded |
| Generation unplanned capability loss factor (UCLF) |
Plan (%) |
≤ 4,2v |
5,13 |
4,34 |
not achieved |
| Distribution system average interruption duration index (SAIDI) |
Plan |
≤ 42,3 |
73,7 |
51,40 |
not achieved |
| Distribution system average interruption frequency index (SAIfi) |
Plan |
≤ 22,8 |
33,72 |
25,20 |
not achieved |
| Rand/megawatt hour (before embedded derivatives) |
Budget |
≤ 183,00 |
189,25 |
160,90 |
not achieved |
Socio-
economic |
Eskom trainees/bursars (learner pipeline) |
Target |
≤ 4 000 |
5 368 |
5 136 |
exceeded |
| Number of engineering trainees/apprentices
(part of learner pipeline above) |
Target |
≤ 3 000 |
4 5631 |
4 3651 |
exceeded |