Business and sustainability performance review  
EXECUTING THE BUILD PROGRAMME  
 
Integrated strategic electricity planning | Investment portfolio | Build programme highlights and lowlights  
 
Environmental impact assessments | Lands and rights | Looking forward | Co-generation programme
 
Nuclear | Other projects | Primary energy for new build | Research | Forward looking commitments
   
 
Looking forward    
   
 
Current planned capacity expansion (MW)

This table indicates the calendar years when new generation capacity is planned to be commissioned.

MW 2008  2009 2010 2011 2012 2013 2014 2015 2016 Total 
Camden (coal-fired)1 400                  400 
Grootvlei (coal-fired)1 590  585               1 175 
Komati (coal-fired)1 120  240 310 285           955 
Ankerlig (OCGT)2   740               740 
Gourikwa (OCGT)2   296               296 
Arnot (coal-fired)3 90  60 30             180 
Medupi (coal-fired)         798 1 596 798 1 596   4 788 
Bravo (coal-fired)           803 1 606 803 1 606 4 818 
Ingula (pumped-storage)           1 352       1 352 
Lima (pumped-storage)               375 1 125 1 500 
Wind farm (renewable)     100             100 
Annual total MW 1 200  1 921 440 285 798 3 751 2 404 2 774 2 731 16 304 
   
 
     
  Current planned capacity expansion  
     
   
 
  1. 1 Return-to-service power station.
  2. 2 Open-cycle gas turbine.
  3. 3 Capacity upgrade.
   
 